THE PROBLEM WITH GLASS SCMs
| UNIT COST RESEARCH PROJECT | ||||
| Phase | Time | Cost | ||
|---|---|---|---|---|
| Phase 1 - Market Assessment | 2 Weeks | $9,000 | ||
|
• Identify local recycling facilities and contacts
• Secure suppliers of glass for proposed facility
|
||||
| Phase 2 - Disposal Cost Assessment | 1 Week | $13,000 | ||
|
• Collect samples of glass from selected suppliers
• Determine contamination level and disposal cost
|
||||
| Phase 3 - Electric Cost Assessment | 1 Week | $6,000 | ||
|
• Create utility bill calculator
• Determine electric cost for proposed market
|
||||
| Total Project Cost | 4 Weeks | $28,000 | ||
| PATHWAY TO PRODUCING GLASS SCMS | |||